Siding replacement: what is behind it matters most
What a re-side includes, how to count squares of siding, why flashing and the wall wrap decide whether it lasts, and what a bid must say.
By RoofElm Editorial Team Updated 7 min read
- One siding square
- 100 square feet of wall
- Behind the siding
- Wall wrap and flashing
- Order of work
- Roof and gutters first
- Pre-1978 homes
- Check for lead paint
In short
A siding replacement strips the old cladding, inspects and repairs the wall sheathing, installs a water-resistive barrier and flashing, and then hangs the new siding and trim. Siding is sold by the square, 100 square feet of wall, and you size it from wall area minus the openings. The siding is the visible part, but the wrap and flashing behind it keep water out of the wall. Fix the roof and gutters first, and plan windows and siding together: see window replacement.
What a siding replacement includes
A re-side is a wall job, not a paint job. The crew removes the old siding and trim, looks at the sheathing underneath, and replaces what is wet or soft. They then install a water-resistive barrier, flash every opening, and put on the new siding, corner posts, trim, and caulk or paint. Siding that goes over old siding can hide rot, so ask each bidder whether the bid is a tear-off or a cover-over.
- Tear-off and disposal: old siding, old trim and nails removed and hauled away.
- Sheathing repair: wet or rotted boards or panels cut out and replaced.
- Weather barrier and flashing: the layer that sheds water that gets behind the siding, and the metal or tape at windows, doors and penetrations.
- Siding, trim and soffit: the visible surface, with the brand, product line and color in the bid.
- Finish: caulk, paint or touch-up, and cleanup of nails and scraps.
The usual order of work runs from the top of the house down, and from the structure outward.
- Roof edge, fascia and gutters are repaired or replaced so water leaves the wall.
- Windows and doors are replaced or flashed, if they are part of the plan.
- Old siding comes off, and the sheathing is checked and repaired.
- The wall wrap and flashing go on, lapped from the bottom up.
- Siding, trim and corners are installed, then caulked and painted as the maker directs.
Sizing the job in squares
Siding is sold by the square, the same unit roofers use: 100 square feet. The formula is wall area, plus gable triangles, minus openings, divided by 100. The numbers below are for an example house, so use your own measurements.
| Step | Math | Result |
|---|---|---|
| Walls: perimeter times height | 2 × (40 + 30) × 9 | 1,260 sq ft |
| Two gables, half of 30 × 8 each | 2 × (30 × 8 ÷ 2) | 240 sq ft |
| Openings: 10 windows at 15, 2 doors at 21 | 150 + 42 | 192 sq ft |
| Net area | 1,260 + 240 − 192 | 1,308 sq ft |
| Squares | 1,308 ÷ 100 | 13.08 squares |
| With an example 10% allowance | 13.08 × 1.10 | 14.4 squares |
The 10 percent allowance is an example, not a standard, because cuts and waste depend on the product and the shape of the house. Ask the installer to state the allowance and to order whole pieces and boxes. If one bid's squares are far from your number, ask why.
Choosing a material
Common sidings are vinyl, fiber cement, engineered wood, solid wood and metal. Each has a different cost, maintenance routine and installation need. We do not rank them, because the right one depends on your climate, your budget, your neighborhood's rules and how often you are willing to paint.
| Material | What to know | Ask about |
|---|---|---|
| Vinyl | Not painted, can crack in cold or warp near heat reflected from some windows. | Gauge, color range and nailing |
| Fiber cement | Heavy, needs paint, and cutting it makes silica dust. | Dust control and finish warranty |
| Engineered or solid wood | Takes paint and can be repaired, but needs upkeep. | Primer, back-priming and caulk |
| Metal | Light and low upkeep, can dent. | Gauge and finish warranty |
Every product has an installation manual, and the warranty often depends on following it. Ask the installer to show you the manual for the product in your bid.
The wall behind the siding
Water gets behind all siding sooner or later, so the wall is built to shed it. The water-resistive barrier, often called house wrap, and the flashing are lapped like shingles: each upper piece goes over the one below it, so water runs down and out. Flashing at windows, doors, roof-to-wall joints and penetrations is where most wall leaks start. Ask the contractor how each will be flashed, and take photos before the siding covers it.
With the siding off, the wall is open, which is the time to add insulation or air sealing. Continuous rigid insulation outside the sheathing changes the thickness at windows, doors and trim, and the details must be planned. Read insulating exterior walls before you sign, and ask for the extra thickness to be in the bid.
Safety, lead paint and permits
If the house was built before 1978, the paint under the siding may contain lead, and the EPA's renovation rule applies to paid work that disturbs painted surfaces. Ask the contractor for their EPA Lead-Safe certification, and read the EPA page. Some older siding, especially cement shingles, may also contain asbestos. Do not cut, break or sand siding you suspect of it, and ask for testing first.
Re-siding often needs a permit, and some areas, such as wildfire zones, limit the materials. Ask your building office, and see permits and inspections. Wall work means ladders or scaffolding, and a fall is the main risk. Keep ladders and metal tools away from overhead power lines.
What drives the price and what to ask
Wall area and shape
Height, gables, many corners and many openings add labor and trim.
Material and trim
The siding product, the trim boards and the finish change the price more than the nails do.
Hidden damage
Wet sheathing and rotted corners are found only after the old siding is off. The bid should price repairs in advance.
- Ask each bidder for the same scope: the squares number, the product line, the barrier, the flashing and the trim.
- Ask how the sheathing repair is priced, per sheet or per square foot, and who decides when it is needed.
- Ask who pulls the permit, who is lead-safe certified for a pre-1978 house, and how nails and scraps are cleaned up.
- Ask for the manufacturer's warranty and the installer's labor warranty separately, in writing.
- Compare line by line with the estimate reading guide, and put your quote into the improvement payback calculator before you count on savings.
Re-siding is crew work for most homes. Replacing a few damaged boards or panels on a low wall is a job for a careful owner, but a whole wall means ladders, scaffolding, flashing and a manual you must follow.
Common questions
Can new siding go over old siding?
Sometimes, but it hides moisture damage and changes the depth at windows and doors. Ask each bidder whether the bid is a tear-off or a cover-over, and why.
How do I figure out how many squares of siding I need?
Add wall area and gable triangles, subtract the windows and doors, and divide by 100. Ask the installer for an allowance for cuts and waste.
Should I replace windows and siding together?
Often, because the flashing at each window is part of both jobs. Plan them as one project, even if the work is done in two stages.
Do I need a permit to replace siding?
Often yes, and some areas limit materials. Call your building office before you sign.
Sources
- U.S. Department of Energy: Re-Side Right, a systems approach to high-performance re-siding projects
- U.S. Department of Energy: Water managed walls
- U.S. Department of Energy: Drainage plane behind exterior wall cladding
- U.S. Department of Energy: Continuous rigid insulation sheathing and siding
- EPA: Lead Renovation, Repair and Painting Program
- EPA: Renovation, Repair and Painting Program, contractors
Reference list checked on November 19, 2026 for relevance. This article gives no code section numbers, product ratings or prices on purpose: they change, so read the installation manual for your product and ask your building office.
Next on the job
-
Project
Window replacement
Insert or full-frame, U-factor and SHGC on the label, measuring, and what a bid must say.
-
Project
Insulating exterior walls
Dense-pack from inside or outside, sheathing at re-siding, plus moisture and lead-safe checks.
-
Guide
Read a contractor estimate
Scope, named materials, allowances and exclusions: what every home improvement bid should say.